Site Visit in Scotland

August 2019

As ever, good clear weather in Scotland.
Our site visits consist of a good meeting centring around works progressed over the last 4 to 5 weeks, ensuring the construction programme.
Progress this last term has been that many of the new stone quions are installed around windows and wall corners, blockwork has begun for the extension and internal studwork has progressed significantly

With the internal first floor installed within the main barn, the contractor has been constructing a jig for the main feature scissor trusses.
Ensuring these are right is crucial to the scheme; 5 of these will run down the main floor of the property, intending to separate out the key areas of the home including kitchen, dining area and living area.